Shaikh Khalifa Causeway Bridge load-out and installation
Load-out and Installation of the Shaikh Khalifa Causeway Bridge in Bahrain
Marine Heavy Lift Partners performed the complete engineering of the seafastening design and did the hydrostatic calculations. We also wrote detailed procedures in a method statement and were responsible for the barge operation.
Summary
| Year | 2002 |
| Operation | Shaikh Khalifa Causeway Bridge load-out and installation |
| Client | MCS / Brambles Heavy Contracting |
| Responsibility | seafastening design, engineering, hydrostatic calculations, barge operation. |